FG Begins 36-Month Carter Bridge Reconstruction

The Federal Government has officially handed over the construction of a brand-new Carter Bridge in Lagos to China Civil Engineering Construction Corporation (CCECC), as part of President Bola Ahmed Tinubu’s commitment to protecting critical infrastructure and ensuring the safety of Nigerians.

The event took place at Carter Bridge, Lagos Island, Lagos State, on Wednesday.

The Minister of Works, Senator David Umahi, said the decision to reconstruct the bridge became necessary after years of alarming structural investigations revealed worsening defects beneath both the Carter Bridge and the 3rd Mainland Bridge.

A statement issued by his Senior Special Assistant on Media, Francis Nwaze, quoted him as saying that investigations into the underwater structural elements of the bridges began as far back as 2013, with another assessment carried out in 2019.

The reports, he said, showed that the defects were increasing at what experts described as “geometrical progression.”

“The past administration commissioned an investigation of what was happening with the structural elements below the water, and that was in 2013. And the very disturbing defects were noticed in Carter Bridge and 3rd Mainland Bridge,” Umahi stated.

Advertisement

He explained that upon assumption of office, the present administration immediately engaged geologists and specialist divers to conduct further underwater investigations, which confirmed that some piles supporting the bridges had already shifted from their pile caps.

“It’s just like the hip of the leg is cut off,” the Minister explained while describing the severity of the damage.

Umahi said extensive consultations were held with bridge experts, stakeholders and members of the National Assembly, including foreign professionals, to determine the best solution.

Experts, according to him, advised that repairing the Carter Bridge would cost almost twice the amount required to build a completely new structure. Following a detailed technical analysis, the Federal Government approved the construction of a new modern bridge.

He revealed that part of the new Carter Bridge will feature a world-class cable-stayed design to improve navigation and add aesthetic value to Lagos.

Advertisement

“We decided that a section of this Carter Bridge will be a cable bridge. You see the cable bridge we see overseas, very beautiful, and that is to enhance our navigational activities,” he said.

The Minister disclosed that the project is expected to last 36 months.

He praised Tinubu for what he described as bold leadership and commitment to infrastructure renewal across the country.

“So we are here to commend the president, president of first, president of infrastructure, the president of second tenure,” Umahi declared.

The project, valued at N545 billion, will be financed through a combination of Federal Government counterpart funding and external borrowing, with 30 per cent to be paid by the Federal Government and 70 per cent sourced externally.

Umahi further stated that due process was strictly followed in selecting the contractor, noting that seven firms were invited while six submitted bids, including Julius Berger.

Advertisement

According to him, CCECC emerged as the most technically and commercially viable company.

“The CECC was technically and commercially most viable. And that’s why the BPP recommended them and the Federal Executive Council has awarded the project to them,” he said.

The Minister directed the company to immediately mobilise to the site while assuring Nigerians that the Ministry would closely monitor the project monthly to ensure compliance with all technical and safety standards.

“By the authority of our president, President Bola Ahmed Tinubu, GCFR, and with gratitude to God Almighty, it is our prayer that this which the president had started, will last 36 months.

“It is the president who has started this work, and God will give him enablement and the second tenure to complete this project to the glory of God,” Umahi added.

Meanwhile, the Minister also announced an emergency closure of one carriageway of the Eko Bridge following severe structural damage caused by illegal sand miners.

He disclosed that illegal dredging activities around the bridge led to the destruction of several supporting piles after miners struck one of the pile caps with a barge.

Umahi explained that the damage has weakened a section of the bridge, resulting in dangerous cracks and structural instability that could threaten lives if urgent action is not taken.

As a precautionary measure, he directed that one full carriageway of the Eko Bridge be shut down by midnight on Sunday, May 10, 2026, while the unaffected carriageway remains open to traffic.

He further disclosed that the Federal Government has already designed an emergency technical solution involving the lifting of an entire bridge span to expose and repair the damaged sections beneath.

According to him, Buildwell Construction, which has extensive experience handling bridge lifting operations on the Eko Bridge, will execute the emergency repairs alongside underwater structural investigations by specialist divers.

The Minister assured Lagosians that President Tinubu has been fully briefed on the situation and directed that the matter be treated as an emergency.